An A3 report is a one-page document that describes a problem, its root causes, the chosen solutions and the plan to implement them. It comes from Toyota and is named after the paper size: A3, 297 × 420 mm (about 11.7 × 16.5 inches). The single page forces a team to think sharply and to agree on the facts. An A3 is not a form you fill in; it is a way of thinking that you make visible.
At Toyota, people came to the conclusion that every problem inside an organisation can, and must be, summarised on a single piece of paper. In this way all involved employees look at the problem through the same lens. The thinking becomes more focused and better structured. Writing on one A3 forces you to formulate the problem and the steps to the solution clearly and concisely.
The A3 report is the backbone of Lean problem solving. It guides a team from the first signs of a problem to a tested solution and a check that the result holds. It does this on one page that everyone can read in a few minutes. The A3 is also used for strategy, as you can read in Hoshin Kanri with A3.

A3 paper size. A3 is 297 × 420 mm. In the United States the closest size is Tabloid or Ledger, 11 × 17 inches. The format is not the point; the discipline of one page is.
Left side, right side. Most A3s read from top left to bottom right. The left half describes the problem, the facts and the root causes. The right half describes the solutions, the plan and how you will check the result. A reader who only sees the left half should already agree that the problem is real.
There is no definitive standard for an A3 template, but often the following ten subjects end up on an A3 project charter. The name of the project and the project leader go in the header of the page.
1. Reason for action. Why are we doing this? Describe the background and the trigger. The problem is recognised by the people involved.
2. Current situation. What is happening now? Use data, or go and collect it. How big is the problem? For example, what percentage of the deliveries is wrong or too late.
3. Goal. What result do you want? When is the problem solved? Which Critical to Quality items (customer requirements) do you address? Make the goal measurable.
4. Analysis of structural (root) causes. Why does the problem exist? Use brainstorming, the 5 Whys and an Ishikawa (fishbone) diagram to get past the symptoms.
5. Solutions. How are we going to solve it? Name the solutions that address the root causes and describe each one.
6. Quick fix. If the situation needs immediate relief, describe the temporary measure here. A quick fix stops the bleeding while the structural solution is built.
7. Realisation plan (implementation plan). Who does what, and by when? Make an action list with owners and dates.
8. Planning and participants. Who is in the team and what is each person’s role? A clear division of tasks prevents misunderstandings.
9. Follow-up actions. What happens if the goal is not reached? Follow-up actions investigate whether the proposed changes and adjustments actually deliver the best results.
10. Evaluation. How will you measure whether the solution works? Which indicators do you track, and how often? When the process shows deviating results, you use the evaluation to bring it back under control.
The seven-box variant. Many English-language sources use a shorter A3 with seven boxes that follow Plan-Do-Check-Act: background, current condition, goal, root cause analysis, countermeasures, effect confirmation and follow-up. It is the same logic in fewer boxes. Choose the layout that your organisation will actually use, and keep it.
An A3 and DMAIC fit together well. The ten subjects map onto the five phases:
In a DMAIC project the A3 is the project charter at the start and the storyboard during the project. At the end it is the one-page summary of what you did and what it delivered. In Lean the same A3 follows the PDCA cycle. DMAIC comes from Six Sigma and is used in Lean Six Sigma; Lean uses PDCA, Kaizen and DMAIC alongside each other, and the A3 works with all of them.
A parcel depot promises next-day delivery. Too many parcels miss that promise.
Reason for action. Customer complaints about late parcels rose over the last quarter. The sales team hears it from large web shop clients.
Current situation. Of 12,000 parcels a week, 8% arrive a day late. Most late parcels come in after the 19:00 cut-off from two web shops. A further share is caused by scanning errors at the sorting belt.
Goal. Fewer than 2% late parcels within three months, measured weekly.
Analysis of root causes. 5 Whys with the inbound team: the two web shops’ collection lorry leaves their warehouse late because their packing shift ends at 18:30. Scanning errors occur because labels are printed at low resolution and the scanner rejects them.
Solutions. Move the collection from the two web shops to 17:30 and add a second, later collection. Ask the web shops to print labels at a higher resolution; test with one shop first.
Quick fix. For two weeks, a second sorter hand-scans rejected parcels so they still make the night run.
Realisation plan. Transport planner changes the collection times by week 2. Account manager agrees the label change by week 3. Team leader trains the sorters on the new scanner setting by week 2.
Planning and participants. Project leader: operations manager. Team: transport planner, account manager, team leader sorting, one sorter.
Follow-up actions. If late parcels stay above 2% after week 8, review the other web shops’ cut-off times.
Evaluation. Weekly chart of the late-parcel percentage on the team board, reviewed in the Monday meeting.
Your own A3 uses your own data.
A strong A3 uses pictures where words would take too long. A flowchart maps the process and shows where it stalls. A graph shows the trend of the problem and later the effect of the solution. A fishbone diagram shows the causes at a glance. A photo of the workplace often says more than a paragraph. Keep text short; let the visuals carry the story.
At the start of the improvement project you do not yet have all the necessary information, and you cannot fill in all ten subjects. An A3 project charter is updated throughout the whole improvement project with new information. New data changes the analysis; a failed test changes the solution. That is normal. The A3 is a storyboard of the project, not a report you write afterwards.
In many organisations an A3 has an owner and a coach. The owner writes it; the coach asks questions and does not give answers. That conversation is where the learning happens.
Writing a good A3 takes practice, especially the left half. Start the Free A3 training and work through it with a template and examples.
Related: Hoshin Kanri with A3
It is one sheet of A3 paper that tells the whole story of a problem: what is wrong, why, what you will do about it and how you will check that it worked.
Little. A project charter is the A3 at the start of a project, with the problem, goal and team. As the project runs, the same page grows into the full A3 report with analysis, solutions and results.
Yes. The free A3 training on this site includes a template and walks you through the ten subjects of an A3 project charter step by step.
After the paper size, 297 × 420 mm (about 11.7 × 16.5 inches). The single sheet keeps the problem-solving story short, so the whole team can read it in a few minutes.
There is no fixed standard. A common A3 project charter in Lean training has ten subjects, from the reason for action, the current situation and the goal to the root causes, the solutions, a realisation plan and the evaluation. Many companies use a shorter seven-box version based on PDCA. Both follow the same logic: problem, causes, countermeasures, check.
Yes. The sections map directly onto Define, Measure, Analyze, Improve and Control. Many Lean Six Sigma projects use the A3 as the project charter and the one-page final report.